Building permits, Zacapa
Latest, Q4 202414permitsAnnual release
vs Q3 2024−60.0%35
vs Q4 2023−22.2%18
Highest since 202366permitsQ1 2024 · INE
Lowest since 202314permitsQ4 2024 · INE
Over time
permitsYear on yearQ1 2023 to Q4 2024Each quarterly figure over the span you pick, or under Change each against the same quarter a year earlier; source: INE.
Recent quarters
The latest quarters, newest first, each with its change on the one before when one publisher gives both.
- Q4 202414permits−60.0% (worse)
- Q3 202435permits+133.3% (better)
- Q2 202415permits−77.3% (worse)
- Q1 202466permits+266.7% (better)
- Q4 202318permits−25.0% (worse)
- Q3 202324permits+33.3% (better)
- Q2 202318permits−45.5% (worse)
- Q1 202333permits
By department
The same measure in each department, shaded on the map and ranked in the list with its share of their sum.
- 7 to 14
- 15 to 23
- 38 to 70
- 72 to 121
- 1,914
- No figure
Related
Other figures from this topic, each with its latest value, its period and its publisher.
- Permitted floor area, national total2,454,227m²+2.5%vs Q3 2024betterQ4 2024INE(go to the source)
- Building permits, national total2,772permits−4.9%vs Q3 2024worseQ4 2024INE(go to the source)
- GDP, manufacturingQ125.0BThe publisher marks this figure as preliminary2025 p/Banguat(go to the source)
- GDP, mining and quarryingQ3.8BThe publisher marks this figure as preliminary2025 p/Banguat(go to the source)