Skip to content

Latest figures

What is the PEG-5-2025 tender and what are its terms?

According to the cited documentsEnergy and water

Capacity sought in PEG-5

~1,400 MW

Supply from May 1, 2030MEM/FUNDESA

PEG-5-2025 is the largest supply tender in the country's history. Its terms of reference were approved by Resolution CNEE-270-2024 (30 October 2024); it seeks ~1,400 MW of guaranteed capacity and associated energy, with supply from May 1, 2030; contracts run up to 15 years for new plants and up to 5 years for existing ones. The bidding rules and the evaluation manual are in Resolution CNEE-108-2025; EEGSA publishes the process documentation on its website.

Read moreRead less
  • Terms of reference

    Resolution CNEE-270-2024

    Oct 30, 2024MEM/FUNDESA
  • Contract term (new / existing)

    Up to 15 years / up to 5 years

    PEG-5-2025MEM/FUNDESA
  • Bidding rules and evaluation manual

    Resolution CNEE-108-2025

    2025MEM/FUNDESA

Sources

  • MEM

    Desarrollo Energético y Ambiental en Guatemala, alojada por FUNDESA

    fundesa.org.gtAccessed Aug 19, 2026Go to the source
  • CNEE

    PEG-5-2025 Licitación Abierta

    cnee.gob.gtAccessed Aug 19, 2026Go to the source