According to the cited documentsEnergy and water
Guaranteed capacity contracted in PEG-4
~399.27 MW
Awarded Aug 2023; entry into service 2026–2028MEM/FUNDESAPEG-4-2022, awarded in August 2023, contracted ~399.27 MW for the guaranteed capacity block, entering operation between 2026 and 2028 under 15-year contracts. Prices came in below US$90/MWh on a monomic basis, with a record US$20.32/MWh in the energy-only bid. The project detail is in Resolution CNEE-196-2023, cited by the AMM.
Read moreRead less
- Contract term15 yearsPEG-4-2022MEM/FUNDESA
- Monomic price< US$90/MWhPEG-4-2022MEM/FUNDESA
- Record energy-only priceUS$20.32/MWhPEG-4-2022MEM/FUNDESA