How long can a shift be, and can I run the plant 24/7?

According to the cited documentsTo be confirmedSetting up a plant

Maximum day shift

8 h/day, 48 h/week

Labor Code in forceCódigo de Trabajo

The Labor Code sets the day shift at a maximum of 8 hours a day and 48 a week; the night shift at 6 hours and 36 a week; the mixed shift at 7 hours and 42 a week; overtime carries a 50% premium. The implication for plant design, is that a 24/7 operation requires four crews or a structural overtime bill. Source: Labor Code, Decree 1441, articles 116 (day shift 'no more than eight hours a day, nor more than forty-eight hours a week in total'; night shift 'six hours a day … thirty-six hours a week'), 117 (mixed shift 'seven hours a day … forty-two hours a week') and 121 (overtime 'paid at least fifty percent above the minimum wages or the higher wages agreed by the parties'), text published by the MCD.

Read moreRead less
  • Night / mixed shift6 h/36 h · 7 h/42 hLabor Code in forceCódigo de Trabajo
  • Overtime premium+50%Labor Code in forceCódigo de Trabajo

Sources

  • Código de Trabajo

    Decreto 1441 y reformas · texto publicado por el Ministerio de Cultura y Deportes

    • Maximum day shift
    • Night / mixed shift
    • Overtime premium
    mcd.gob.gtAccessed Sep 6, 2026Go to the source