Six lessons from the public record: (1) early, state-run consultation closes; late and judicialized does not, Oxec is the only closed cycle, Escobal reached consultation 5+ years after the conflict and the answer was 'no'; (2) consultation is not a referendum, but it is not a formality either, Fénix shows that running it while excluding the amparo claimants and under a state of siege produces paper, not peace; (3) recognizing the collective subject is step zero, Escobal and Ixquisis both began by denying the indigenous people; (4) do not pay for the social license, earn it, Mining Secrets documented what buying it costs and what it costs more when it comes out (OFAC, loss of shareholder control); (5) the worst-case budget already has Guatemalan figures: 9 years of care and maintenance over 264.5 Moz (Escobal), withdrawal after 8 years (Cambalam), a US$499 M arbitration lost (El Tambor), a transnational public apology (Tahoe); (6) monitor consultation as a country risk, not only a project risk.
What distinguishes projects that survive the social license test in Guatemala?
According to the cited documentsSocial licence
Sources
Prensa Libre MEM finalizó consultas a 11 comunidades por caso Oxec
Earthworks Xinka people say no to the Escobal mine
Prensa Comunitaria Dic-2021, El Estor concluye consulta sobre proyecto Fénix; comunidades Q'eqchi' la invalidan
Forbidden Stories Mining Secrets
Prensa Libre Guatemala gana arbitraje internacional y evita pagar US$499 millones
Soy502 Hidro Santa Cruz anuncia retiro de Guatemala