The closing of the Oxec consultation and its lessons

Dossier
Social license and prior consultation23-licencia-social.md
Domain
Social license and prior consultationlicencia-social
Room
Law/ley
Audited
Audited

The Ministry of Energy and Mines (MEM) consulted 11 Q'eqchi' communities in September 2017, in Spanish and Q'eqchi', and reported it to the Amparo Chamber on 11 December 2017, with 5 agreements signed by the State, the company and the communities; minister Luis Chang called it 'historic' on 12 December 2017 and MEM clarified that consulting means 'reaching agreements', not a yes/no vote. Oxec operates and Oxec II finished construction: it is the only large case where the full cycle (court order → state consultation → agreements → operation) closed. The counterpoint: community defender Bernardo Caal Xol was sentenced to 7 years and 4 months and released in March 2022, and a self-convened community consultation in Cahabón (August 2017) rejected the projects (record outside this pass).

The research is written in English; quoted figures, source names and the titles of legal instruments stay in the language their source published them in.

Figures

Oxec consultationPrensa Libre / La Hora
11 communities; 5 agreements; held Sep 20172017

Sources

Related records

This layer is research: read from public sources by the archive's own team, every claim cited with the date it was consulted, and audited where it is marked so. It has not entered the verified store — no figure here was fetched back from its source or stamped with a retrieval time — so it wears no red provenance numeral and never mixes with the verified figures.